Contract List - 2026

  • Institusi Nama Project PT Pimpro Contract Due Date Delivery Date Close / BAST Keterangan Counter
    1 Poltekpel Surabaya Helicopter Rescue Simulator TMU Alham Ihza Fahim 26 May 26 21 Nov 26 - - - 78
    hari lagi
    2 BP3 Bitung Bridge BP3 Bitung ARI Eugene Benedictus Taslim 16 Mar 26 13 Aug 26 - - - 22
    hari terlewat
    3 BP3 Ambon Bridge + Engine (1+7) BP3 Ambon ARI M.Fajri Ramdhani 17 Mar 26 13 Aug 26 - - - 22
    hari terlewat
    4 SMKP Samarinda SMKP Samarinda - Bridge 240+CBT 1+15 ARI M.Fajri Ramdhani 20 Nov 25 26 Dec 25 - 06 Feb 26 - Selesai
  • Institusi Nama Project PT Pimpro Contract Due Date Delivery Date Close / BAST Keterangan Counter
    5 KP Karawang KKP Karawang - Radar Arpa ARI M.Fajri Ramdhani 11 Nov 25 25 Dec 25 - 19 Jan 26 - Selesai
    6 Poltektrans SDP Palembang Laboratorium CBA Poltektrans SDP Palembang III Deri Ramadhan 14 Nov 25 15 Dec 25 - 06 Jan 26 - Selesai
    7 SMKP Lintas Nusantara Ship Bridge Simulator ARI M.Fajri Ramdhani 29 Jul 25 12 Dec 25 - 15 Dec 25 - Selesai
    8 Dinas Pendidikan Sulawesi Selatan Bridge Sim SMKN 9 Makassar ARI M.Fajri Ramdhani 04 Aug 25 12 Dec 25 - 15 Dec 25 - Selesai
  • Institusi Nama Project PT Pimpro Contract Due Date Delivery Date Close / BAST Keterangan Counter
    9 KP Karawang Bridge, DT Engine, GMDSS, Lab Bahasa ARI M.Fajri Ramdhani 29 Aug 25 06 Dec 25 - 19 Jan 26 - Selesai
    10 Poltekpel Malahayati Aceh Perlengkapan VR TMU Nur Rizal Rivaldi 08 Sep 25 05 Dec 25 - 15 Dec 25 - Selesai
    11 Poltekpel Barombong Bridge 240°, 120° +120° Tug ARI M.Fajri Ramdhani 12 Sep 25 30 Nov 25 - 01 Dec 25 - Selesai
    12 Dispeta Seven Cs OTI Rizal Fitrah Nugraha 29 Oct 25 07 Nov 25 - 20 Nov 25 - Selesai
  • Institusi Nama Project PT Pimpro Contract Due Date Delivery Date Close / BAST Keterangan Counter
    13 Dishidro Base Editor 2 Lcs OTI Rizal Fitrah Nugraha 22 Oct 25 31 Oct 25 - 11 Nov 25 - Selesai
    14 Dishidro Upgrade Base Editor 3 Lcs OTI Rizal Fitrah Nugraha 22 Oct 25 31 Oct 25 - 11 Nov 25 - Selesai
    15 PIP Makassar KALK TMU Eugene Benedictus Taslim 07 Aug 25 09 Oct 25 - 25 Sep 25 - Selesai
    16 Poltekpel Barombong Pass-Hub 10 Titik TMU Ronald Tarigan 29 Sep 25 02 Oct 25 - 27 Oct 25 - Selesai
  • Institusi Nama Project PT Pimpro Contract Due Date Delivery Date Close / BAST Keterangan Counter
    17 PPI Curug Pass-Hub 10 Titik TMU Ronald Tarigan 28 Sep 25 30 Sep 25 - 27 Oct 25 - Selesai
    18 PIP Semarang Pass-Hub 10 Titik TMU Ronald Tarigan 22 Sep 25 26 Sep 25 - 30 Sep 25 - Selesai
    19 Poltekpel Malahayati Aceh Pass-Hub 10 Titik III Ronald Tarigan 18 Sep 25 25 Sep 25 - 30 Sep 25 - Selesai
    20 Poltekpel Banten Pass-Hub 10 Titik TMU Ronald Tarigan 22 Sep 25 25 Sep 25 - 09 Oct 25 - Selesai
  • Institusi Nama Project PT Pimpro Contract Due Date Delivery Date Close / BAST Keterangan Counter
    21 Politeknik Perkeretaapian Indonesia Madiun Pass-Hub 10 Titik TMU Ronald Tarigan 16 Sep 25 24 Sep 25 - 30 Sep 25 - Selesai
    22 Poltrada Bali Pass-Hub 10 Titik TMU Ronald Tarigan 22 Sep 25 24 Sep 25 - 30 Sep 25 - Selesai
    23 Poltekpel Sulut Pass-Hub 10 Titik III Ronald Tarigan 18 Sep 25 24 Sep 25 - 30 Sep 25 - Selesai
    24 Politeknik Transportasi Darat Indonesia STTD Pass-Hub 10 Titik TMU Ronald Tarigan 15 Sep 25 22 Sep 25 - 30 Sep 25 - Selesai
  • Institusi Nama Project PT Pimpro Contract Due Date Delivery Date Close / BAST Keterangan Counter
    25 PIP Makassar Pass-Hub 10 Titik TMU Ronald Tarigan 15 Sep 25 22 Sep 25 - 30 Sep 25 - Selesai
    26 STIP Jakarta IGF Desktop 10 + 1 STIP Jakarta ARI Rizal Fitrah Nugraha 13 Aug 25 21 Sep 25 - 22 Sep 25 - Selesai
    27 STIP Jakarta Pass-Hub 10 Titik TMU Ronald Tarigan 13 Sep 25 19 Sep 25 - 23 Sep 25 - Selesai
    28 Museum Geologi - ESDM Revitalisasi Multimedia Museum ARI Bagus Winarno 27 Sep 24 26 Dec 24 - 24 Dec 24 - Selesai
  • Institusi Nama Project PT Pimpro Contract Due Date Delivery Date Close / BAST Keterangan Counter
    29 Universitas Jambi Fishing Sim 180 + 45 TMU M.Fajri Ramdhani 08 Oct 24 21 Dec 24 - 03 Dec 24 - Selesai
    30 Dinas Pendidikan Sulawesi Selatan Desktop Engine Simulator 001 TMU M.Fajri Ramdhani 12 Jun 24 09 Dec 24 - 30 Sep 24 - Selesai
    31 Dinas Pendidikan Sulawesi Selatan Bridge Sim SMK Selayar 001 TMU M.Fajri Ramdhani 12 Jun 24 09 Dec 24 - 30 Sep 24 - Selesai
    32 Dinas Pendidikan Sulawesi Selatan Bridge Sim SMK Bantaeng 001 TMU M.Fajri Ramdhani 12 Jun 24 09 Dec 24 - 30 Sep 24 - Selesai
  • Institusi Nama Project PT Pimpro Contract Due Date Delivery Date Close / BAST Keterangan Counter
    33 STIP Jakarta PENGADAAN PERMESINAN PENGGERAK POKOK UNTUK KAPAL NELAYAN TMU Yudha Wangsamenggalla 21 Oct 24 25 Nov 24 - 11 Nov 24 - Selesai
    34 STIP Jakarta Virtual Reality STIP ARI Eugene Benedictus Taslim 21 Oct 24 08 Nov 24 - 05 Nov 24 - Selesai
    35 Dinas Pendidikan Kepulauan Riau Bridge Sim SMK SMKN 1 Bunguran Timur 001 TMU M.Fajri Ramdhani 04 Jul 24 31 Oct 24 - 29 Oct 24 - Selesai
    36 Poltekpel Surabaya Smartport Simulation TMU Elvin Mudhita 01 Apr 24 01 Oct 24 - 16 Oct 24 - Selesai
  • Institusi Nama Project PT Pimpro Contract Due Date Delivery Date Close / BAST Keterangan Counter
    37 DITKAPEL IDSea TMU Deri Ramadhan 24 Apr 24 01 Oct 24 - 28 Nov 24 - Selesai
    38 Dinas Navigasi (Disnav-Tual) Software Caris Hips and Sips - New License OTI Rizal Fitrah Nugraha 11 Jun 24 31 Jul 24 - 15 Aug 24 - Selesai
    39 PUSHIDROSAL 2 lcs x Trainning PCC OTI Rizal Fitrah Nugraha 04 Jul 24 17 Jul 24 - 17 Jul 24 - Selesai
    40 SSDM Binjas Polri Alat Ukur Ujian Kemampuan Jasmani Berbasis Digital TMU Bagus Winarno 29 Feb 24 28 Jun 24 - 28 Jun 24 - Selesai
  • Institusi Nama Project PT Pimpro Contract Due Date Delivery Date Close / BAST Keterangan Counter
    41 Poltekpel Barombong Ship Stability TMU Vian Fitri Yambodo 12 Feb 24 11 May 24 - 08 May 24 - Selesai
    42 PUSHIDROSAL Pengadaan Versi PCC TA 2024 OTI Rizal Fitrah Nugraha 26 Mar 24 01 Apr 24 - 02 Apr 24 - Selesai

Project List - 2026

Helicopter Rescue Simulator - (TMU)

Poltekpel Surabaya // Pimpro : Alham Ihza Fahim
Contract : 26 May 26
Due Date : 21 Nov 26
Delivery Date : -
Close/BAST : -
Lihat Keterangan
78 hari lagi

Bridge BP3 Bitung - (ARI)

BP3 Bitung // Pimpro : Eugene Benedictus Taslim
Contract : 16 Mar 26
Due Date : 13 Aug 26
Delivery Date : -
Close/BAST : -
Lihat Keterangan
22 hari terlewat

Bridge + Engine (1+7) BP3 Ambon - (ARI)

BP3 Ambon // Pimpro : M.Fajri Ramdhani
Contract : 17 Mar 26
Due Date : 13 Aug 26
Delivery Date : -
Close/BAST : -
Lihat Keterangan
22 hari terlewat

SMKP Samarinda - Bridge 240+CBT 1+15 - (ARI)

SMKP Samarinda // Pimpro : M.Fajri Ramdhani
Contract : 20 Nov 25
Due Date : 26 Dec 25
Delivery Date : -
Close/BAST : 06 Feb 26 -
Lihat Keterangan
252 hari terlewat

KKP Karawang - Radar Arpa - (ARI)

KP Karawang // Pimpro : M.Fajri Ramdhani
Contract : 11 Nov 25
Due Date : 25 Dec 25
Delivery Date : -
Close/BAST : 19 Jan 26 -
Lihat Keterangan
253 hari terlewat

Laboratorium CBA Poltektrans SDP Palembang - (III)

Poltektrans SDP Palembang // Pimpro : Deri Ramadhan
Contract : 14 Nov 25
Due Date : 15 Dec 25
Delivery Date : -
Close/BAST : 06 Jan 26 -
Lihat Keterangan
263 hari terlewat

Ship Bridge Simulator - (ARI)

SMKP Lintas Nusantara // Pimpro : M.Fajri Ramdhani
Contract : 29 Jul 25
Due Date : 12 Dec 25
Delivery Date : -
Close/BAST : 15 Dec 25 -
Lihat Keterangan
266 hari terlewat

Bridge Sim SMKN 9 Makassar - (ARI)

Dinas Pendidikan Sulawesi Selatan // Pimpro : M.Fajri Ramdhani
Contract : 04 Aug 25
Due Date : 12 Dec 25
Delivery Date : -
Close/BAST : 15 Dec 25 -
Lihat Keterangan
266 hari terlewat

Bridge, DT Engine, GMDSS, Lab Bahasa - (ARI)

KP Karawang // Pimpro : M.Fajri Ramdhani
Contract : 29 Aug 25
Due Date : 06 Dec 25
Delivery Date : -
Close/BAST : 19 Jan 26 -
Lihat Keterangan
272 hari terlewat

Perlengkapan VR - (TMU)

Poltekpel Malahayati Aceh // Pimpro : Nur Rizal Rivaldi
Contract : 08 Sep 25
Due Date : 05 Dec 25
Delivery Date : -
Close/BAST : 15 Dec 25 -
Lihat Keterangan
273 hari terlewat

Bridge 240°, 120° +120° Tug - (ARI)

Poltekpel Barombong // Pimpro : M.Fajri Ramdhani
Contract : 12 Sep 25
Due Date : 30 Nov 25
Delivery Date : -
Close/BAST : 01 Dec 25 -
Lihat Keterangan
278 hari terlewat

Seven Cs - (OTI)

Dispeta // Pimpro : Rizal Fitrah Nugraha
Contract : 29 Oct 25
Due Date : 07 Nov 25
Delivery Date : -
Close/BAST : 20 Nov 25 -
Lihat Keterangan
301 hari terlewat

Base Editor 2 Lcs - (OTI)

Dishidro // Pimpro : Rizal Fitrah Nugraha
Contract : 22 Oct 25
Due Date : 31 Oct 25
Delivery Date : -
Close/BAST : 11 Nov 25 -
Lihat Keterangan
308 hari terlewat

Upgrade Base Editor 3 Lcs - (OTI)

Dishidro // Pimpro : Rizal Fitrah Nugraha
Contract : 22 Oct 25
Due Date : 31 Oct 25
Delivery Date : -
Close/BAST : 11 Nov 25 -
Lihat Keterangan
308 hari terlewat

KALK - (TMU)

PIP Makassar // Pimpro : Eugene Benedictus Taslim
Contract : 07 Aug 25
Due Date : 09 Oct 25
Delivery Date : -
Close/BAST : 25 Sep 25 -
Lihat Keterangan
330 hari terlewat

Pass-Hub 10 Titik - (TMU)

Poltekpel Barombong // Pimpro : Ronald Tarigan
Contract : 29 Sep 25
Due Date : 02 Oct 25
Delivery Date : -
Close/BAST : 27 Oct 25 -
Lihat Keterangan
337 hari terlewat

Pass-Hub 10 Titik - (TMU)

PPI Curug // Pimpro : Ronald Tarigan
Contract : 28 Sep 25
Due Date : 30 Sep 25
Delivery Date : -
Close/BAST : 27 Oct 25 -
Lihat Keterangan
339 hari terlewat

Pass-Hub 10 Titik - (TMU)

PIP Semarang // Pimpro : Ronald Tarigan
Contract : 22 Sep 25
Due Date : 26 Sep 25
Delivery Date : -
Close/BAST : 30 Sep 25 -
Lihat Keterangan
343 hari terlewat

Pass-Hub 10 Titik - (III)

Poltekpel Malahayati Aceh // Pimpro : Ronald Tarigan
Contract : 18 Sep 25
Due Date : 25 Sep 25
Delivery Date : -
Close/BAST : 30 Sep 25 -
Lihat Keterangan
344 hari terlewat

Pass-Hub 10 Titik - (TMU)

Poltekpel Banten // Pimpro : Ronald Tarigan
Contract : 22 Sep 25
Due Date : 25 Sep 25
Delivery Date : -
Close/BAST : 09 Oct 25 -
Lihat Keterangan
344 hari terlewat

Pass-Hub 10 Titik - (TMU)

Politeknik Perkeretaapian Indonesia Madiun // Pimpro : Ronald Tarigan
Contract : 16 Sep 25
Due Date : 24 Sep 25
Delivery Date : -
Close/BAST : 30 Sep 25 -
Lihat Keterangan
345 hari terlewat

Pass-Hub 10 Titik - (TMU)

Poltrada Bali // Pimpro : Ronald Tarigan
Contract : 22 Sep 25
Due Date : 24 Sep 25
Delivery Date : -
Close/BAST : 30 Sep 25 -
Lihat Keterangan
345 hari terlewat

Pass-Hub 10 Titik - (III)

Poltekpel Sulut // Pimpro : Ronald Tarigan
Contract : 18 Sep 25
Due Date : 24 Sep 25
Delivery Date : -
Close/BAST : 30 Sep 25 -
Lihat Keterangan
345 hari terlewat

Pass-Hub 10 Titik - (TMU)

Politeknik Transportasi Darat Indonesia STTD // Pimpro : Ronald Tarigan
Contract : 15 Sep 25
Due Date : 22 Sep 25
Delivery Date : -
Close/BAST : 30 Sep 25 -
Lihat Keterangan
347 hari terlewat

Pass-Hub 10 Titik - (TMU)

PIP Makassar // Pimpro : Ronald Tarigan
Contract : 15 Sep 25
Due Date : 22 Sep 25
Delivery Date : -
Close/BAST : 30 Sep 25 -
Lihat Keterangan
347 hari terlewat

IGF Desktop 10 + 1 STIP Jakarta - (ARI)

STIP Jakarta // Pimpro : Rizal Fitrah Nugraha
Contract : 13 Aug 25
Due Date : 21 Sep 25
Delivery Date : -
Close/BAST : 22 Sep 25 -
Lihat Keterangan
348 hari terlewat

Pass-Hub 10 Titik - (TMU)

STIP Jakarta // Pimpro : Ronald Tarigan
Contract : 13 Sep 25
Due Date : 19 Sep 25
Delivery Date : -
Close/BAST : 23 Sep 25 -
Lihat Keterangan
350 hari terlewat

Revitalisasi Multimedia Museum - (ARI)

Museum Geologi - ESDM // Pimpro : Bagus Winarno
Contract : 27 Sep 24
Due Date : 26 Dec 24
Delivery Date : -
Close/BAST : 24 Dec 24 -
Lihat Keterangan
617 hari terlewat

Fishing Sim 180 + 45 - (TMU)

Universitas Jambi // Pimpro : M.Fajri Ramdhani
Contract : 08 Oct 24
Due Date : 21 Dec 24
Delivery Date : -
Close/BAST : 03 Dec 24 -
Lihat Keterangan
622 hari terlewat

Desktop Engine Simulator 001 - (TMU)

Dinas Pendidikan Sulawesi Selatan // Pimpro : M.Fajri Ramdhani
Contract : 12 Jun 24
Due Date : 09 Dec 24
Delivery Date : -
Close/BAST : 30 Sep 24 -
Lihat Keterangan
634 hari terlewat

Bridge Sim SMK Selayar 001 - (TMU)

Dinas Pendidikan Sulawesi Selatan // Pimpro : M.Fajri Ramdhani
Contract : 12 Jun 24
Due Date : 09 Dec 24
Delivery Date : -
Close/BAST : 30 Sep 24 -
Lihat Keterangan
634 hari terlewat

Bridge Sim SMK Bantaeng 001 - (TMU)

Dinas Pendidikan Sulawesi Selatan // Pimpro : M.Fajri Ramdhani
Contract : 12 Jun 24
Due Date : 09 Dec 24
Delivery Date : -
Close/BAST : 30 Sep 24 -
Lihat Keterangan
634 hari terlewat

PENGADAAN PERMESINAN PENGGERAK POKOK UNTUK KAPAL NELAYAN - (TMU)

STIP Jakarta // Pimpro : Yudha Wangsamenggalla
Contract : 21 Oct 24
Due Date : 25 Nov 24
Delivery Date : -
Close/BAST : 11 Nov 24 -
Lihat Keterangan
648 hari terlewat

Virtual Reality STIP - (ARI)

STIP Jakarta // Pimpro : Eugene Benedictus Taslim
Contract : 21 Oct 24
Due Date : 08 Nov 24
Delivery Date : -
Close/BAST : 05 Nov 24 -
Lihat Keterangan
665 hari terlewat

Bridge Sim SMK SMKN 1 Bunguran Timur 001 - (TMU)

Dinas Pendidikan Kepulauan Riau // Pimpro : M.Fajri Ramdhani
Contract : 04 Jul 24
Due Date : 31 Oct 24
Delivery Date : -
Close/BAST : 29 Oct 24 -
Lihat Keterangan
673 hari terlewat

Smartport Simulation - (TMU)

Poltekpel Surabaya // Pimpro : Elvin Mudhita
Contract : 01 Apr 24
Due Date : 01 Oct 24
Delivery Date : -
Close/BAST : 16 Oct 24 -
Lihat Keterangan
703 hari terlewat

IDSea - (TMU)

DITKAPEL // Pimpro : Deri Ramadhan
Contract : 24 Apr 24
Due Date : 01 Oct 24
Delivery Date : -
Close/BAST : 28 Nov 24 -
Lihat Keterangan
703 hari terlewat

Software Caris Hips and Sips - New License - (OTI)

Dinas Navigasi (Disnav-Tual) // Pimpro : Rizal Fitrah Nugraha
Contract : 11 Jun 24
Due Date : 31 Jul 24
Delivery Date : -
Close/BAST : 15 Aug 24 -
Lihat Keterangan
765 hari terlewat

2 lcs x Trainning PCC - (OTI)

PUSHIDROSAL // Pimpro : Rizal Fitrah Nugraha
Contract : 04 Jul 24
Due Date : 17 Jul 24
Delivery Date : -
Close/BAST : 17 Jul 24 -
Lihat Keterangan
779 hari terlewat

Alat Ukur Ujian Kemampuan Jasmani Berbasis Digital - (TMU)

SSDM Binjas Polri // Pimpro : Bagus Winarno
Contract : 29 Feb 24
Due Date : 28 Jun 24
Delivery Date : -
Close/BAST : 28 Jun 24 -
Lihat Keterangan
798 hari terlewat

Ship Stability - (TMU)

Poltekpel Barombong // Pimpro : Vian Fitri Yambodo
Contract : 12 Feb 24
Due Date : 11 May 24
Delivery Date : -
Close/BAST : 08 May 24 -
Lihat Keterangan
846 hari terlewat

Pengadaan Versi PCC TA 2024 - (OTI)

PUSHIDROSAL // Pimpro : Rizal Fitrah Nugraha
Contract : 26 Mar 24
Due Date : 01 Apr 24
Delivery Date : -
Close/BAST : 02 Apr 24 -
Lihat Keterangan
886 hari terlewat